Indiana's Construction Stormwater General Permit INRA00000 expires December 17, 2026. Contractors must verify their project's individual five-year coverage term, submit renewal information or a new Notice of Intent ninety days before that project-specific expiration date through IDEM's Regulatory ePortal, and maintain compliant SWPPPs and controls during the transition.

Pro SWPPP prepares stormwater plans for contractors nationwide.

Not sure whether your project needs a SWPPP? Take the SWPPP quiz.

What does the December 17, 2026 expiration mean for Indiana SWPPPs and permit coverage?

The December 17, 2026 date marks when Indiana's current Construction Stormwater General Permit expires as a regulatory document. It does not automatically extend or terminate coverage for individual construction projects. Each project covered under the CSGP has its own five-year coverage term that begins when the Indiana Department of Environmental Management approves the project's Notice of Intent.

IDEM administers the CSGP under Indiana's NPDES authority. The current permit, effective December 18, 2021, governs construction activity involving land disturbance of one acre or more, including clearing, grading, excavation, and related work that generates sediment and construction runoff.

IDEM has publicly noticed a draft replacement construction general permit, but the draft is not yet final or effective. Contractors should not rely on draft provisions, deadlines, or forms until IDEM issues the final replacement permit.

Contractor reviewing stormwater permit documents at construction site office

How do contractors determine their Indiana SWPPP project's actual coverage expiration date?

A project's coverage expiration date is five years from the date IDEM approved the NOI, not the general permit's December 17, 2026 expiration. The current permit states that project effective dates established under the prior permit remain in effect and must be renewed ninety days before the established expiration date, unless IDEM accepts a later date.

Contractors should check their project's NOI approval documentation or IDEM correspondence for the specific coverage start date. If the project began under the previous permit cycle, the renewal deadline may arrive well before December 2026.

For projects that will continue construction beyond their five-year coverage term, the permit requires submission of a new NOI. Once the five-year coverage term is reached, coverage is considered expired and a new NOI must be submitted for construction activity to continue.

See the SWPPP plan request form.

What must contractors submit to renew Indiana SWPPP permit coverage?

Contractors must submit renewal information or a new NOI through IDEM's Regulatory ePortal ninety days before their project coverage expires, unless IDEM determines that a later date is acceptable. The current permit requires the NOI and supporting documents to be submitted online through the Regulatory ePortal and provides for online payment of the applicable fee.

The submission must include information about the construction activity, site location, operator details, and confirmation that a stormwater pollution prevention plan has been prepared. The SWPPP itself is maintained on-site and made available for inspection; it is not submitted with the NOI.

Contractors should not wait until December 2026 to address their project's coverage. The ninety-day advance submission requirement applies to the project's individual expiration date, which may be months or years before the general permit expires.

What happens to active Indiana SWPPPs after the general permit expires?

The current permit contains an authorization-continuation provision. Its conditions remain effective and enforceable after December 17, 2026, if the permittee timely submitted an NOI for coverage and IDEM has not, through no fault of the permittee, issued a new permit by the expiration date.

This continuation is not a blanket extension for every contractor. It depends on timely submission of renewal information and the other stated conditions. Contractors who fail to submit required renewal information ninety days before their project coverage expires cannot rely on the continuation provision.

IDEM's replacement permit will establish new requirements, deadlines, and procedures. Contractors should monitor IDEM's program page for the final permit and any transition guidance.

Inspector documenting stormwater controls with clipboard at construction site

What SWPPP and site obligations continue during Indiana's permit transition?

Permit renewal does not replace the contractor's obligation to maintain the stormwater pollution prevention plan, erosion and sediment controls, inspections, stabilization, and other requirements applicable to the active project. The SWPPP must remain on-site, accessible, and updated to reflect current site conditions and control measures.

A project's inspection schedule, control-measure maintenance, and record-keeping obligations continue without interruption. The precise obligations depend on the permit version and project circumstances.

Pro SWPPP prepares plans, files permits, performs inspections, and keeps records. Customer crews install and maintain the physical controls; Pro SWPPP documents and inspects compliance.

How is Indiana's CSGP different from EPA's construction permit for SWPPPs?

Indiana's CSGP applies to eligible construction stormwater discharges in Indiana and is administered by IDEM under Indiana's NPDES authority. EPA's federal construction-stormwater permit is relevant where EPA is the permitting authority, but it is not the permit governing ordinary projects covered by IDEM's Indiana CSGP.

Contractors should not apply EPA permit conditions, deadlines, or procedures to Indiana projects unless IDEM's permit explicitly incorporates them. Indiana's permit has its own NOI process, coverage terms, inspection requirements, and compliance obligations.

Request a project-specific SWPPP estimate.

What uncertainties remain about Indiana's 2026 SWPPP permit transition?

IDEM's replacement permit was publicly noticed, but the available information identifies it as a draft or public-comment document rather than a final effective permit. The final replacement permit's effective date, renewal deadlines, transition provisions, NOI procedures, SWPPP requirements, and any revised conditions should be confirmed in IDEM's final permit before relying on them.

Contractors should verify each project's current NOI coverage and expiration date rather than assuming that all projects share December 17, 2026, as their individual deadline. The draft permit may include revised conditions, but those provisions are not operative until IDEM issues the final version.

What else should Indiana contractors know about the 2026 SWPPP permit transition?

Does every Indiana construction project need CSGP coverage and an SWPPP?

IDEM states that construction activity involving land disturbance of one acre or more requires coverage under the CSGP. Smaller projects may still require coverage if they are part of a larger common plan of development or sale that will ultimately disturb one acre or more.

Can contractors continue work if their Indiana SWPPP coverage expires before the replacement permit is final?

No. Once a project's five-year coverage term expires, coverage is considered expired and a new NOI must be submitted for construction activity to continue. The general permit's continuation provision does not extend individual project coverage beyond its five-year term without timely renewal submission.

What should contractors do if they are unsure of their Indiana SWPPP project's coverage status?

Review the NOI approval documentation or contact IDEM to confirm the project's coverage start date and expiration date. Do not assume that all projects share the December 17, 2026 general permit expiration as their individual deadline. If the project's five-year term is approaching, begin the renewal process at least ninety days in advance.

Will the replacement permit change Indiana SWPPP or inspection requirements?

The draft replacement permit may include revised conditions, but those provisions are not operative until IDEM issues the final version. Contractors should verify the final replacement permit's effective date, renewal deadlines, transition provisions, NOI procedures, SWPPP requirements, and any revised conditions before relying on them.

Discuss the SWPPP scope for your project.

By Derek E. Chinners, CPESC — Founder & Stormwater Consultant, Pro SWPPP, LLC