TCEQ STEERS is back online. If it ever goes down again, call Pro SWPPP at 833.GET.SWPP. We still file your N.O.I. In October 2026, TCEQ took STEERS offline for a statewide data center audit, and Texas construction ground to a halt for anyone who didn’t know the manual path. We filed through it the whole time. As America’s #1 SWPPP and the #1 authority on SWP3s in Texas, here’s what happened, what’s still in effect, and exactly what we do the next time the portal goes dark.

Not sure what you need? Speak with a CPESC-certified SWPPP expert now.

Why did TCEQ shut STEERS down in 2026?

STEERS, the State of Texas Environmental Electronic Reporting System, is the portal Texas operators use to file Notices of Intent, Notices of Change, Notices of Termination and Low Rainfall Erosivity Waivers under the Construction General Permit TXR150000. Before the shutdown it issued most stormwater authorizations automatically, often within minutes of payment.

On September 21, 2026, Governor Abbott directed TCEQ to halt permits for data center projects while their water and power demand was reviewed. STEERS kept auto-authorizing stormwater NOIs with no human review, and reports in October showed that more than two dozen authorizations had still gone to data center projects. TCEQ suspended those authorizations and, on October 20, took the STEERS filing application offline for every applicant. TCEQ’s stated purpose was to audit data center applications and rebuild STEERS so staff review applications before an authorization issues.

Every Texas operator was locked out, not just data centers. Projects that needed an NOI to break ground had one lawful option left: the manual episodic waiver filing.

Derek E. Chinners, CPESC, Founder and Stormwater Consultant at Pro SWPPP, who filed Texas SWP3 NOIs through the 2026 TCEQ STEERS outage

What is the TCEQ episodic waiver?

Federal NPDES rules require electronic reporting, but 40 CFR 127.15 lets a state grant an episodic waiver of that requirement for up to 60 days when its electronic system is down. On October 28, 2026, TCEQ’s Interim Executive Director issued that waiver, citing the prolonged STEERS outage.

It allows applications under three TPDES general permits to be submitted by email, on the approved TCEQ form:

The waiver is valid through Monday, December 28, 2026. It is a manual review process. A TCEQ staff member opens each email, checks the form by hand, matches the CN and RN in Central Registry, confirms the signatory and checks the fee. There is no error message and no confirmation screen. One missing field sends the packet to the back of the line.

Is STEERS back up, and what’s still in effect?

Yes. STEERS is back online and accepting stormwater filings again. Three things from the outage still matter:

  • Expect more staff review. TCEQ rebuilt STEERS so staff can review applications before authorization.
  • The MSGP renewal deadline is December 28, 2026. TCEQ extended it from November 12 for TXR050000 permittees.
  • Data center projects still follow the Governor’s directive. Filing by email doesn’t get around it.

Authorizations issued during the outage stand on their own paperwork. If yours was filed by email, keep the sent email, every attachment, the ePay receipt and TCEQ’s acknowledgment in the SWP3.

Need your SWP3 written and your NOI filed this week? Hit the SWPPP Easy Button.

If STEERS goes down again, can Pro SWPPP still file my N.O.I. or N.O.T.?

Yes. Now or in the future, a dark portal doesn’t stop a Pro SWPPP client. We file through whatever path TCEQ opens, and we have the forms ready before you need them.

For an N.O.I. (new coverage), we run the same playbook we used all through the 2026 outage:

  1. Write the SWP3 first. The NOI certifies under penalty of law that the plan already exists.
  2. Complete the approved TCEQ NOI form. CN, RN, receiving water, MS4, acreage and SIC code, all checked against Central Registry.
  3. Route the signature correctly. A 30 TAC §305.44 signer, or a delegate already filed under §305.128.
  4. Pay and document the fee in ePay. The fee doesn’t go away when the portal does.
  5. File under the episodic waiver. We email the complete packet to the permit-specific TCEQ address and track it to authorization.
  6. Send the MS4 copy and post the site notice. The CGP requires both no matter how the NOI was filed.

Under the 2023 CGP, STEERS coverage starts on submission, but paper coverage starts seven days after a complete NOI is postmarked. We treat an emailed NOI the same way: no soil disturbance until seven days after TCEQ receives the complete packet. It’s the only reading that holds up if an inspector asks.

For an N.O.T. (ending coverage), TCEQ’s 2026 waiver named new applications, not terminations. If the portal goes down while your project is wrapping up, we prepare your N.O.T. on TCEQ’s approved form and keep your inspections and records current until coverage legally ends. We file the N.O.T. through the first path TCEQ opens. Coverage doesn’t end, and neither do your obligations, until the N.O.T. is accepted.

For an N.O.C. (changes), we handle it the same way. We prepare it on the approved form, document the change in the SWP3 within the permit deadline, and file it the moment TCEQ allows.

What should a Texas contractor do if a project can’t wait?

  1. Confirm the project isn’t tied to a data center. If it is, no filing path exists until the directive lifts.
  2. Get the SWP3 written. Nothing can be filed until the plan exists. Pro SWPPP delivers in 72 hours, or 24 with rush.
  3. Hand us the filing. We prepare, sign-route, pay, file and track the NOI under whatever process TCEQ has open.
  4. Keep inspecting. Every 7 days, or every 14 days plus within 24 hours of a half-inch rain. Outage or not.

The full statewide rules are in our Texas SWPPP requirements guide. When STEERS is up, see our walkthrough of filing the NOI in STEERS.

Not sure what you need?

Some projects need a full SWP3 and NOI. Some qualify for a Low Rainfall Erosivity Waiver and need no SWP3 at all. Some are part of a larger common plan and don’t know it yet. The fastest way to find out is a 15-minute call with a CPESC-certified SWPPP expert.

Book your call with a CPESC SWPPP expert now. Or call 833.GET.SWPP.

Frequently asked questions about TCEQ STEERS outages

Is TCEQ STEERS back up?

Yes. STEERS went offline on October 20, 2026, for a data center audit and is back online. TCEQ rebuilt it so staff can review applications before an authorization issues.

Why did STEERS go down in 2026?

Under the Governor’s September 21, 2026, data center directive, TCEQ took STEERS offline to audit data center applications after authorizations were still being issued automatically. The shutdown applied to every applicant.

Can I file a Texas NOI if STEERS goes down again?

In 2026, TCEQ issued an episodic waiver allowing CGP, MSGP and concrete production applications on the approved TCEQ form by email, valid through December 28, 2026. Pro SWPPP files through whatever path TCEQ opens. Call 833.GET.SWPP.

Can Pro SWPPP file my N.O.T. while STEERS is down?

We prepare it on TCEQ’s approved form, keep your inspections current until coverage ends, and file it through the first path TCEQ opens. Coverage and inspection duties continue until the N.O.T. is accepted.

When is the 2026 MSGP renewal deadline?

TCEQ extended the TXR050000 renewal deadline from November 12 to Monday, December 28, 2026.

By Derek E. Chinners, CPESC — Founder & Stormwater Consultant, Pro SWPPP, LLC · America’s #1 SWPPP

Related: What is a SWPPP? · When is a SWPPP required? · Texas SWPPP requirements · Industrial SWPPP and the Texas MSGP